From first drawing to steel on your Thai site – step by step

Project delivery process

From first drawing to steel on your Thai site – step by step

Twelve clear steps, one project engineer and a schedule you can plan around. This is how every World Steel project for Thailand runs – from design to delivery.

48 hquotation
1–3 wksapproval drawings
3–6 wksfabrication & QC
3–5 dayssea freight
8–12 wkstypical order to site

Design

  1. 01

    Day 1–2

    Enquiry & site brief

    Send drawings, a sketch or just the size, location and use. We confirm wind zone, soil and crane needs, delivery term and target dates – in English or Thai, on LINE, WhatsApp or e-mail.

    Enquiry checklistSite location review

  2. 02

    Within 48 h

    Concept design & quotation

    Our engineers size the frame, purlins, bracing and fire protection, then price steel, paint, packing and freight. You receive one clear offer, CIF or DDP.

    QuotationPreliminary layoutSteel weight estimate

  3. 03

    Week 1–3

    Approval drawings & calculations

    After order we issue general arrangement, anchor-bolt plan, base reactions and structural calculations to Thai loading (DPT 1311 wind, 1301/1302 seismic) or your code.

    GA drawingsAnchor-bolt planCalculation report

  4. 04

    Week 2–4

    Thai engineer sign-off & permits

    Your Thai licensed engineer (Council of Engineers) reviews and signs for the building permit or the estate approval. We answer questions and revise quickly.

    Signed drawings (by client’s engineer)Revision log

Build

  1. 05

    Week 2–4

    Shop drawings & materials

    The approved design is modelled in Tekla; every plate and bolt is detailed. Steel is drawn from stock or ordered from certified mills.

    Tekla modelShop drawingsMill certificates

  2. 06

    Week 3–8

    Fabrication

    CNC cutting and drilling, automated beam welding and assembly in our 20,000 m² factory – with a fabrication slot booked when you order.

    Production scheduleWeekly progress photos

  3. 07

    Throughout

    Quality control – six stages

    Incoming material, cutting/drilling, fit-up, welding (VT/UT), blasting and painting each inspected against the ITP. Non-conformities are tagged Hold and closed by NCR.

    ITPInspection recordsWeld NDT reports

  4. 08

    Week 5–8

    Blasting & painting

    Sa 2.5 blasting, paint system to ISO 12944 with TOA or your specified brand, intumescent coating where fire rating is required; film thickness recorded.

    DFT recordsPaint data sheets

Deliver

  1. 09

    Week 7–9

    Packing & loading

    Members piece-marked and bundled by erection sequence; containers and flat-racks loaded to a packing list you receive in advance.

    Packing listLoading photosErection drawings

  2. 10

    3–5 days at sea

    Sea freight (CIF)

    From southern Vietnam to Laem Chabang, Bangkok, Map Ta Phut or Songkhla. We send B/L, invoice, insurance and ATIGA Form D for 0 % ASEAN import duty.

    Bill of ladingInsuranceForm D

  3. 11

    3–7 days

    Thai customs & trucking (DDP)

    With DDP we clear Thai customs, pay duties and VAT, and truck the steel to your site in the order your erection team needs it.

    Customs entryDelivery schedule

  4. 12

    On site

    Erection support & handover

    Anchor-bolt templates, erection drawings and supervision on request; touch-up paint, as-built drawings and the full quality dossier at handover.

    As-built drawingsQuality dossierTouch-up kit

Responsibilities

Who does what

TaskWorld SteelClient
Structural design & calculations✓Review
Thai engineer sign-off & building permitSupport✓
Foundations & anchor-bolt settingAnchor-bolt plan & templates✓
Fabrication, QC & painting✓Optional witness inspection
Sea freight to a Thai port✓ (CIF / DDP)–
Thai customs, duties & trucking✓ (DDP)✓ (CIF)
ErectionDrawings & supervision on request✓ (own or partner contractor)
Roofing & cladding–✓ (local supplier)

Documents

Documents you receive

  • Structural calculation report
  • General arrangement & anchor-bolt drawings
  • Shop and erection drawings (PDF + DWG/IFC on request)
  • Mill certificates (EN 10204 3.1 on request)
  • Inspection & test plan and inspection records
  • Welding procedure and welder qualifications
  • Paint system specification and DFT records
  • Packing list, bill of lading, insurance, ATIGA Form D
  • As-built drawings and touch-up instructions

Thailand

Planning notes for Thai projects

Monsoon season

From about May to October, plan erection windows and covered storage; we can sequence deliveries to suit.

Thai public holidays

Songkran (April) and New Year close ports and customs for several days – we build them into the schedule.

Auspicious dates

Many Thai owners hold a ceremony for raising the first column (Sao Ek). Tell us the date and we deliver the first columns ahead of it.

Estate & municipal approvals

Allow time for the estate or local authority review; our quick drawing revisions keep it short.